ADR 0045 — Event-based rescheduling of the dev agent, and the circuit breaker

Context​

Dogfooding's P1 finding #10, verbatim from docs/missions/dogfooding-mission.md:659:

A dev agent processes ONE task and stops. :work is only triggered on activation and on accepting parallelization; report_done opens the gate and doesn't reschedule; no Oban worker redispatches it. Cap per module: 1 task, or 2 with parallelization.

The practical consequence is in :396-398 of the same harvest: Phase 10 ran in batches — a human reactivating execution (or restarting the engine) between each task, because nothing in the system took the agent from the open PR back to "free to claim." Finding #11 (:660, P2) describes the symptom of trying to work around it from the outside: reactivating doesn't redispatch :work (the supervisor returns :existing) and still creates an orphaned session.

Two facts verified in the code, BEFORE designing, shaped the entire decision:

  1. The worktree is per AGENT, not per task. WorktreeManager.add_worktree/3 deletes the agent's previous worktree before creating the next one, and QaLeadServer/SecOpsAgentServer find it via DevAgentState.find_by_task_id/2 while the gate runs. Claiming the next task as soon as the PR opens would physically destroy the worktree the gate is still scanning. That decided that an open PR can't free the agent — it needs a state that RETAINS the worktree until the gate finishes.
  2. prod/patches.yaml runs 2 engine replicas, and Engine.Dev.Registry is local to the node. An async job (Oban) can run on any replica; resolving "where is this agent's process" via Registry would miss delivery in half the cases in production.

Decision​

The signal is outbox, not an in-process call​

task.gate_resolved (only on TERMINAL outcomes — done/blocked) and task.became_claimable (story promoted, task created under an already-ready story, task unblocked) are outbox lines the api emits, read by the already-existing Engine.Outbox.Drain (aggregate_type gained "task" alongside "session") and routed to the new Engine.Workers.DevAgentWakeWorker — the same mechanism as always, a new handler.

The choice of outbox instead of, for example, the gate calling DevAgentServer.correct/3 directly the way it already does for changes_requested (that in-process call CONTINUES to exist, unchanged) is about survival: an outbox line persists across an engine restart between the verdict and the wake. An in-process call doesn't — and that's exactly the property Phase 12b-6 (rehydration) needs to close the rehydrated awaiting_gate reacting to a gate resolved after the restart.

awaiting_gate is the interlock, not a label​

Open PR → the agent enters awaiting_gate and KEEPS task_id/worktree/branch — nothing claims anything while the gate hasn't resolved. Only the terminal outcome (via task.gate_resolved) releases it, through finish_task/2. The worktree fact from #1 above is the entire reason this state exists.

Delivery via PubSub, not Registry​

Engine.Dev.Wake uses Phoenix.PubSub (already supervised as Engine.PubSub, unused in lib/ until now) — cluster-wide for free, unlike the node-local Registry (fact #2). DevAgentServer subscribes to its own topic in init/1; DevAgentWakeWorker never calls the GenServer directly, always via Wake.deliver/3.

Consciously accepted limit: delivery is AT-MOST-ONCE. If the agent's process is momentarily down when the broadcast happens, the wake is lost and the agent only wakes on the NEXT event. Fully closing this would require :global registration for dev agents — the same thing Engine.Sessions.SessionServer already does, for the same reason — rewriting AgentIo.via/2, DevAgentSupervisor.start_agent and Monitor. Out of scope for this phase; see "what's left for later."

The circuit breaker lives in the engine, not in the api​

backlog.task_blocked's actor.id is WHO BLOCKED IT (qa-agent, secops-agent, qa-lead, or the dev itself) — the api has no way to tell "THIS agent's sequence" apart from it. consecutive_blocked lives in dev_agent_states, incremented in only one place (finish_task/2), because it's the only point through which the agent learns EVERY outcome of its own task — local (ToolLoop) or remote (task.gate_resolved with nextAction: "blocked", the gate's correction cap exhausted). RN-047 details the mechanism and the invariants.

The cap (max_consecutive_blocked) follows the pattern of task_budget_micros — a column on projects, resolved at activation (parameter → project setting → default) — but got what that one never had: a PATCH + a field in Settings. The user's decision: even at the cost of more surface, the breaker's cap is the kind you want to adjust without blindly reactivating execution.

Rearm is the only way out of idle_tripped​

A single click (POST .../agents/:agentId/rearm) — no automatic unlock, same principle as unblock for individual tasks. The api records dev.rearmed with actor: user BEFORE anything is guaranteed to happen in the engine (the same order — engine first, event after — that AcceptParallelizationUseCase already uses, for the same reason: the event log is immutable, and recording before a refusal would leave a lie in it). The engine does NOT emit a second dev.rearmed of its own: that would be the same event counted twice by different actors in the same session. What happens next (claimed something or went back to idle) already gets narrated via dev.working/dev.idle, which the rearm's try_claim/1 triggers.

Consequences​

  • Acceptance of the central requirement: a project with N ready tasks in a module processes all of them in sequence with ONE agent, with no engine restart and no manual reactivation — the chain claim → PR → gate approved → claim next → empty queue → idle → new task → wakes up is deterministic and tested end to end (dev_agent_chain_test.exs), with the REAL outbox/drain/worker/PubSub infrastructure in the middle, not simulated.
  • The dev↔gate correction path (changes_requested) stays exactly as it was — in-process, without outbox. It's the mechanical proof that rescheduling doesn't duplicate that path: task.gate_resolved is only emitted for terminal outcomes, so there's no second line to trigger it.
  • Rehydration stopped being "come back blank": awaiting_gate and working retain or recover whatever made sense to retain; an interrupted working blocks with an honest restart diagnosis instead of silently complaining or trying to resume a ToolLoop that no longer exists.
  • The atomic claim didn't change (FOR UPDATE OF t SKIP LOCKED, backlog.repository.ts) — rescheduling increases WHO attempts the claim (the same agent, more times; two agents of the module waking up together), not the guarantee that already existed. The api's concurrency proof (8 real parallel claims) stays untouched; the new one is on the engine side, over the reaction logic.
  • NoopDevAgentServer stays outside the entire mechanism: never opens a gate, never gets woken up, status fixed at "working". It's an infrastructure smoke test, not a second product to keep in sync with the state machine.

Adversarial review, and what it found​

The implementation went through an independent audit BEFORE leaving the branch — done without feeding the auditor the justifications above, so as not to inherit whoever wrote it's blind spots. It found eight defects, four of them capable of locking up an agent or the boot. All were fixed; the record stays here because the lesson is more useful than the list.

This ADR's decision didn't change. What changed was its implementation, which was wrong at points the tests couldn't reach.

Why the whole suite passed green with four lockups inside: the fakes (FakeWorktreeManager, FakeEngineApiClient) return instantly and always with success. There was no test path for a claim_task that fails, for the ToolLoop's real cost inside init/1, nor for a gate finishing a task outside RecordGateVerdictUseCase. A test that only exercises the happy path measures the absence of typos, not the correctness of the design. The fake gained an error branch and configurable delay along with the fixes.

The four critical ones, for what they teach:

  • Partial state is worse than wrong state. finish_task/2 zeroed task_id but didn't touch status; a transient 5xx on the claim was enough for the agent to end up awaiting_gate with task_id nil — a combination NONE of the three guards accept. The agent stayed half-dead, and the cause was a one-second network failure.
  • init/1 is a boot path, not a place to work. Recovering an interrupted working ran in there, and since start_link/start_child expect :infinity, the whole boot got stuck for the duration of an LLM task. It moved to handle_continue.
  • A funnel that isn't the only funnel isn't a funnel. The design said "the agent learns EVERY outcome of its own task via finish_task/2" — but QaLeadServer blocks by calling MarkTaskBlockedUseCase directly, without going through RecordGateVerdictUseCase, where the emission lived. The emission moved down to the real funnel.
  • I copied the outbox mechanism without copying its reason. The four new emissions didn't use UnitOfWork, even though AppendSessionEventUseCase does — breaking the invariant architecture.md describes as the reason the outbox exists, in a file I edited in this same phase.

What's left for later​

  • :global for dev agents — would close the at-most-once gap of PubSub delivery. Not urgent: the next event (another gate, another claimable task) still reaches an agent that missed a wake, just not immediately.

  • "3 real gates in sequence, no restart" as manual acceptance, not CI. QA Lead and SecOps are LLM judgment — non-deterministic by nature, the same reason ADR 0020 already recorded for Phase 4a's acceptance criterion ("CLOSED, but not deterministic"). What the suite proves is everything DOWNSTREAM of the verdict; dogfooding with real gates remains a human demonstration, recorded in the CHANGELOG.

  • A kill in the middle of the ToolLoop has no automatic resumption, by decision. Turn, messages and worktree edits only exist in memory — there's nothing to resume. Blocking with a diagnosis and leaving a human to decide is the same doctrine that already governs local blocks; a full automatic resumption (redispatching a new ToolLoop on the SAME already-claimed task) would be new autonomy, and CLAUDE.md marks that as an explicit non-goal of Phase 12.

  • The worktree can disappear under a pending approval — finding D5 from the review, consciously accepted, not fixed. The awaiting_gate interlock protects the GATE window, but not the approval pipeline's window: with the dev's autonomy set to manual (the panel toggle allows it), git_commit/git_push stay pending; gates scan the WORKTREE, not the PR, so they can approve, the agent claims the next task and add_worktree/3 deletes the directory — and the human approval, when it comes, runs against a path that no longer exists. Before 12b the agent would stop and the worktree would survive indefinitely.

    It wasn't fixed because the obvious fix — holding the claim while there's a pending proposed_action for that worktree — reintroduces exactly the coupling this phase removed: the agent would go back to depending on external state to decide whether it can work. The path also requires leaving the default: ActivateExecutionUseCase seeds auto_approve for git_commit/git_push/pr_open of every dev agent, so it only reaches whoever changed autonomy by hand. It stays recorded as a known limit; if it shows up in practice, the right fix is for the worktree to be per TASK instead of per agent, which is a structural change and calls for its own ADR.

  • 12b didn't touch findings #12 through #16 from the same harvest (free manual handoff, story promotion — that's Phase 12c —, return to the PO, shared panel tab, approval counter). Out of scope.

References ADR 0005 (the durable-state + rehydration mold this ADR extends to dev agents) and ADR 0020 (the origin of the "never silent reclaim" doctrine and the precedent for manual acceptance of a non-deterministic criterion).